Drain and Vent

Drain and Vent / Every layout

Permits and the rough-in inspection

What happens between pulling the permit and closing the walls.

When you need a permit

New drains, new vents, moving a fixture and adding a bathroom need a permit almost everywhere in the US. Swapping a faucet or a toilet on the same flange usually does not. The building department's website lists what needs one, and many let homeowners pull a plumbing permit for their own house.

The visits

  1. Underground, for a slab: the trench is open, the pipe is in and holding water.
  2. Rough-in: walls and floors open, drains and vents in, the system filled with water or air for the test, supply lines in.
  3. Final: fixtures set and working.

What the inspector looks at

  • The test holding, with no drop.
  • Pipe sizes and the fall on horizontal runs.
  • That every fixture is vented, and how.
  • Fittings turned the right way for the direction of flow.
  • Primer on every PVC joint (the purple ring), cleanouts where needed, nail plates over pipes in studs.
  • Holes and notches in joists and studs within their limits.

A rough-in sheet on the stud answers most of these before they are asked. Find your layout.